New Braunfels utility planning 2 major wastewater infrastructure improvements

By Texas Government Insider 1 min read

New Braunfels Utilities (NBU) is moving forward on two critical wastewater infrastructure projects as part of its five-year $587 million capital improvement plan.
Wooden gazebo beside a misty river among trees in New Braunfels
New Braunfels

NBU is planning a $52.9 million expansion of its North and South Kuehler wastewater treatment plant to combine two existing permits into one discharge permit with a single outfall location. The expansion will increase the facility’s total treatment capacity from its current 7 million gallons per day (MGD) to 9.4 MGD.

Design for the Sam McKenzie Water Reclamation Facility Expansion project is set to begin in fiscal year 2020. Construction is scheduled to start FY 2021 and conclude in FY 2022. Expansion of this facility will increase its treatment capacity from 2.5 MGD to 5 MGD and comply with Texas Commission on Environmental Quality threshold regulations.

Subscribe Free

The Same Type of Intelligence We Bring to Clients — Delivered to Your Inbox

Choose the publications you want to receive, or subscribe to all of them.

"*" indicates required fields

This field is for validation purposes and should be left unchanged.
Publications*